UP-Jeffrey Field Soccer Complex Renovation
Project Number
00-09024.00
Project Status
Trade/Bid Packages
Complete - Architect/Engineer and Design/Build Selection
Complete - Trade/Bid Packages
Campus
University Park
Project Stage
Out to Bid
Project Description
The new soccer operations center will include home and visiting team locker rooms, training, hydrotherapy, strength and conditioning, coaches offices, meeting rooms, restrooms and concessions. The facility will be located adjacent to the existing Jeffrey Field.
Penn State Project Leader Name, Email
Company Name
Massaro Corporation
Contact Name
Michael Clements
Phone
412-689-8569
Email
Project Stage for Trade/Bid Package Information
Waiting for Award
Prequalification
Massaro Prequalification Form to be submitted at the time of bid.
Additional Information
One of the bid packages will be bid through e-Builder as others will be bid through Building Connected. See bid package(s) for details.
BIDDING CONTACT
Dale Wunderley, (412) 287-9341, [email protected]
Bid Due Date and Time
Package Number | Package Name | Pre-Bid Date/Time | Pre-Bid Meeting | Bid Date/Time | Awarded To | Document |
---|---|---|---|---|---|---|
01 | Concrete | Recommended but not Mandatory | Leonard S. Fiore | |||
02 | Structural Steel | Recommended but not Mandatory | Stewart Amos Steel | |||
BP3-01 | Landscaping | Recommended but not Mandatory | Alex's Proscape | |||
BP3-01a | Turf Surfacing | Recommended but not Mandatory | SCOPE REMOVED | |||
BP3-02 | Masonry | Recommended but not Mandatory | Harris Masonry | |||
BP3-03 | Architectural Woodwork | Recommended but not Mandatory | EB Endres | |||
BP3-04 | Roofing | Recommended but not Mandatory | R. H. Marcon, Inc. | |||
BP3-05 | Waterproofing | Recommended but not Mandatory | ||||
BP3-06 | Equipment Screening Systems | Recommended but not Mandatory | Nittany Building Specialties | |||
BP3-07 | Glass & Glazing | Recommended but not Mandatory | Nittany Building Specialties | |||
BP3-08 | Metal Panels | Recommended but not Mandatory | Nittany Building Specialties | |||
BP3-09 | General Trades | Recommended but not Mandatory | ||||
BP3-10 | Tiling | Recommended but not Mandatory | J. P. Phillips, Inc. | |||
BP3-11 | Polished Concrete | Recommended but not Mandatory | Allegheny Installations | |||
BP3-12 | Resilient Athletic Flooring | Recommended but not Mandatory | Degol Carpet & Ceramic Tile | |||
BP3-13 | Soft Flooring | Recommended but not Mandatory | Degol Carpet & Ceramic Tile | |||
BP3-14 | Painting | Recommended but not Mandatory | Whitewater Painting | |||
BP3-15 | Lockers | Recommended but not Mandatory | Shield | |||
BP3-16 | Special Doors | Recommended but not Mandatory | Neff Specialties | |||
BP3-17 | Operable Partition | Recommended but not Mandatory | SCOPE REMOVED | |||
BP3-18 | Roller Shades | Recommended but not Mandatory | ||||
BP3-19 | Elevator | Recommended but not Mandatory | Right Elevator | |||
BP3-20 | Appliances | Recommended but not Mandatory | S. A. Comunale Co., Inc. | |||
BP3-21 | Fire Protection | Recommended but not Mandatory | McClure Company | |||
BP3-22 | Plumbing | Recommended but not Mandatory | G.R. Sponaugle & Sons, Inc. | |||
BP3-23 | Mechanical | Recommended but not Mandatory | Westmoreland Electric | |||
BP3-26 | Electrical | Recommended but not Mandatory | Contract Hardware & Supply | |||
BP3-27 | Doors, Hardware, Openers, Access Readers (Furnish Only) | Recommended but not Mandatory | Neff Specialties | |||
BP3-28 | Toilet Accessories and Partitions (Furnish Only) | Recommended but not Mandatory | Neff Specialties | |||
BP3-29 | Fire Extinguishers and Defibulators (Furnish Only) | Recommended but not Mandatory | Neff Specialties | |||
BP3-30 | Visual Display Units and Projection Screens (Furnish Only) | Recommended but not Mandatory | ||||
BP3-31 | Signage (Furnish Only) | Recommended but not Mandatory | ProBel | |||
BP3-32 | Fall Protection System (Furnish Only) | Recommended but not Mandatory | ||||
BP3-33 | Mobile Storage Shelving (Furnish Only) | Recommended but not Mandatory |