UP-Beaver Stadium Renovation
Project Number
00-09218.00
Project Status
Trade/Bid Packages
Complete - Trade/Bid Packages
Campus
University Park
Project Stage
Out to Bid
Project Description
The primary scope of the Beaver Stadium renovation is on the stadium's West Side. This approach would replace the current West Side of the stadium and provide improved access for broadcasting, greatly improved circulation, new restrooms, upgraded concession offerings, and much-needed premium seating. Included with the West Side replacement are much-needed miscellaneous improvements of the North, East, and South, as listed below. These combined projects will greatly enhance the fan experience and safety and provide significant incremental revenue to fund these improvements.
Penn State Project Leader Name, Email
Company Name
Barton Malow AECOM Hunt Alexander
Contact Name
Malachi Hays
Phone
(313) 618-1128
Email
Project Stage for Trade/Bid Package Information
Waiting for Award
Prequalification
Additional Information
Bid through Building Connected. Prospective bidders should contact the CM team to discuss bid opportunities and receive access to the bid platform.
Bid Due Date and Time
Package Number | Package Name | Pre-Bid Date/Time | Pre-Bid Meeting | Bid Date/Time | Awarded To | Document |
---|---|---|---|---|---|---|
00-02 | ECI - Structural Steel | Sippel | ||||
00-03 | ECI - Electrical | Lighthouse | ||||
00-04 | ECI - Low Voltage | Lighthouse | ||||
00-06 | ECI - Plumbing | McClure | ||||
00-07 | ECI - Mechanical | McClure | ||||
00-08 | Structural Precast ECI | Not Awarded | ||||
00-09 | Deep Foundations ECI | Coastal Drilling East, LLC | ||||
00-10 | Structural Precast ECI | |||||
01-03 | 2024 East Stadium Improvements - Deep Foundations | Recommended but not Mandatory | Coastal | |||
01-04 | 2024 East Stadium Improvements - Site & Excavation | Recommended but not Mandatory | GOH | |||
01-05 | 2024 East Stadium Improvements - Steel | Recommended but not Mandatory | Stewart Amos | |||
01-06 | 2024 East Stadium Improvements - CIP Concrete | Recommended but not Mandatory | PJ Dick | |||
01-07 | 2024 East Stadium Improvements - Plumbing | Recommended but not Mandatory | McClure | |||
01-08 | 2024 East Stadium Improvements - Electrical | Recommended but not Mandatory | Hayden | |||
01-09 | 2024 East Stadium Improvements - Metal Panels | Recommended but not Mandatory | Novinger's | |||
01-10 | 2024 East Stadium Improvements - Masonry | Recommended but not Mandatory | Smith | |||
01-11 | 2024 East Stadium Improvements - General Trades | Recommended but not Mandatory | Novinger's | |||
01-12 | 2024 East Stadium Improvements - Roll-Up Gates | Recommended but not Mandatory | Novinger's | |||
01-13 | 2024 East Stadium Improvements - Canopy | Recommended but not Mandatory | Novinger's | |||
01-14 | 2024 East Stadium Improvements - Paint & Coatings | Recommended but not Mandatory | Saints | |||
01-15 | 2024 East Stadium Improvements - Fire Protection | Recommended but not Mandatory | NOT AWARDED | |||
00-01 | Early Contractor Involvement (ECI) Preconstruction - Selective Structural Demolition | ISI Demolition |