UP-Steam Distribution Program

Project Number
00-09955.00
Project Status
Architect/Engineer and Design/Build Selection
Construction Manager Selection and Other Services
Trade/Bid Packages
Campus
University Park
Project Description

The Steam Distribution Program may encompass seven, or more projects, over an approximate two-year period with an estimated budget of $20 million. The projects will take place at University Park, PA and focus on steam tunnels, steam manholes and hot water distribution conversions. The CM-R will enter into a master commitment with the University to complete each project.

Penn State Project Leader Name, Email
Architect/ Engineer and Design Build Selection
Capital Project (>$10M)
No
Construction Manager Selection and Other Services
Project Stage for Construction Manager Selection and Other Services
RFP
Attachments for Construction Manager Selection and Other Services
Due Date
Trade/Bid Package Information
Project Stage for Trade/Bid Package Information
Announcement
Prequalification

See Section A & Section N of the Project Manual for prequalification information.

Additional Information

Bid through Building Connected. Document distribution and submission will also be through Building Connected. Contact Brian McDowell for access to the bid documents.  

Bid Due Date and Time
Package Number Package Name Pre-Bid Date/Time Pre-Bid Meeting Bid Date/Time Awarded To Document
001 General Trades/Civil Recommended but not Mandatory
002 Mechanical Recommended but not Mandatory