East Halls PH 2-B: Bigler, Curtin, and Packer Renovation

Project Number: 
00-06750.00
Project Stage: 
Out to Bid
Project Description: 

Renovation of three buildings at East Halls: Curtin and Packer Halls each 7-story 69,939 SF residence halls (plus basement), Bigler Hall a five-story 64,210 SF residence hall (plus basement), as well as project site work associated with Phase 2B. 

PSU Project Leader: 
Bid Date and Time: 
Tuesday, October 1, 2019 - 3:00pm
Prequalification: 

Bidders can prequalify through First, Verify at:  https://pq.firstverify.com/Vendor/VendorRegistration   Prequalification is not a requirement to submit a bid but is a requirement to work on the project.  Contact Clayco with any questions. 

Professional Consultant
Company Name: 
DLA+
Contact Name: 
John Sickles
Address: 

Foster Plaza 9, Suite 200, 750 Holiday Drive Pittsburgh, PA 15220

Phone: 
(412) 921-4300
CM Firm
Company Name: 
Clayco, Inc.
Contact Name: 
Ashwin Ramesh
Address: 

2199 Innerbelt Business Center Drive - St. Louis, MO 63114

Phone: 
(814) 441-9475
Previous Bid Packages
Package Number Title Anticipated Document Delivery Pre-Bid Date/Time Pre-Bid Meeting Bid Date/Time Awarded To Document
1 Electrical 09/03/2019 No pre-bid 10/01/2019 3:00 PM
2 Mechanical 09/03/2019 No pre-bid 10/01/2019 3:00 PM
3 Plumbing 09/03/2019 No pre-bid 10/01/2019 3:00 PM
4 Fire Protection 09/03/2019 No pre-bid 10/01/2019 3:00 PM