Visual Arts Building HVAC REplacement

  • Completion - August 2015
  • BOT Approved Amount - $8,000,000

SCOPE:

The project scope included a new hot water plant in the building, new insulated duct work, controls upgrade, piping replacement, and two new air handlers. Electrical modifications were made to support the installation and the building was connected to the campus chilled water system.  During the course of the work, corridor ceilings were replaced and new energy efficient LED light fixtures were installed.